During the first nine weeks we will learn
how to do scale drawings. Then in the second nine weeks we will
learn most of the steps to build and house and we will build a scale
model of the house your groups designs.
1st Nine Weeks Deadlines Feburary 26 House drawing
March 5 Scale Drawing
March 12 Land and Foundations 2nd Nine Weeks Deadlines
March 26 25% House Framing
April 1 50% House Framing
April 9 75% House Framing
April 16
Framing Complete, Electricity, and
Plumbing
April 23 Drywall Complete
April 30 House Complete